The City of San José opened a new dewatering facility at the San José–Santa Clara Regional Wastewater Facility (RWF), supported by a US$177 million investment. The RWF is among the largest wastewater facilities in the western United States, and the project is intended to modernize biosolids processing while reducing site impacts and improving operational reliability.
The new mechanical dewatering system replaces open-air lagoons and drying beds that depended on weather and could take about four years to complete dewatering. By contrast, the enclosed process completes the task in less than a day, enabling timely transport of material off-site for beneficial uses such as compost, fertilizer, or soil amendment. The upgrade reduces biosolids processing from roughly four years to under a day, and the city estimates more than 100,000 tons of biosolids will be produced and transported each year.
Operational changes and site footprint
An odor control system was installed to continuously capture and treat gases released during dewatering, addressing a key concern for nearby communities and on-site workers. The project also consolidates and shrinks the footprint for biosolids handling from over 500 acres to a 10-acre site, freeing up significant land previously committed to drying operations.
The RWF, located in Alviso, treats an average of 110 million gallons of wastewater per day, serving approximately 1.5 million residents and more than 17,000 commercial and industrial customers across eight South Bay cities. It is jointly owned by San José and Santa Clara, with San José’s Environmental Services Department managing operations and the capital program. Over the past decade, the Capital Improvement Program has invested about US$1.2 billion and completed 31 projects, and the facility was recently recognized by the National Association of Clean Water Agencies for five years of perfect compliance with federal and state environmental laws.
Long-term plan and regulatory drivers
The dewatering facility advances recommendations from the 2013 Plant Master Plan, which called for replacing open-air drying beds and lagoons with an enclosed mechanical process. An April 2026 update to the plan extends the planning horizon to 2050 and estimates total program costs through that year at US$3.9 billion, including costs for projects already completed. Among the drivers for increasing costs and additional work needs, the update cites stricter requirements, including the 2024 Nutrient Watershed Permit that sets significantly lower limits on total inorganic nitrogen discharges into San Francisco Bay—limits the plant’s current liquids treatment process could not meet without upgrades.
The dewatering project is part of a broader set of improvements underway at the RWF. Jacobs has been awarded work to replace aging digesters, and Brown and Caldwell is advising on a project to reduce nitrogen in treated water. For the dewatering facility specifically, Brown and Caldwell served as owner advisor, with Walsh Construction as design builder, Black & Veatch as design engineer, and Stantec as program manager.